You are currently here!
  • Home
  • Adobe AD0-E911 AD0-E911 exam questions for practice in 2026 Updated 98 Questions [Q23-Q41]

AD0-E911 exam questions for practice in 2026 Updated 98 Questions [Q23-Q41]

October 6, 2026 latestexam 0 Comments
Rate this post

AD0-E911 exam questions for practice in 2026 Updated 98 Questions

Updated Oct-2026 Premium AD0-E911 Exam Engine pdf – Download Free Updated 98 Questions

Adobe AD0-E911 Exam Overview:

Certification Vendor: Adobe
Exam Name: Adobe Workfront Project Manager Certified Professional
Exam Number: AD0-E911
Real Exam Qty: 50
Available Languages: English
Exam Format: Scenario-based questions, Multiple choice, Online proctored
Exam Duration: 100 minutes
Related Certifications: Adobe Experience Cloud certifications
Adobe Workfront Core Developer Professional
Passing Score: 33/50
Exam Price: $125 USD (global) / $95 USD (India)
Recommended Training: Adobe Experience League – Workfront learning path
Exam Registration: Adobe Certification Portal
Sample Questions: Adobe AD0-E911 Sample Questions
Exam Way: Online proctored (remote, camera required)
Pre Condition: Recommended 6–12 months experience using Adobe Workfront or project/work management tools
Official Syllabus URL: https://certification.adobe.com/certification/project-manager-certified-professional/1320

 

NO.23 A project manager wants to see all of the assignees for each task in a project.
Which field should the manager reference to view all task assignees?

 
 
 

NO.24 Which project status will default the automatic Project Condition to “On Time”?

 
 
 

NO.25 How is the primary assignee of a task determined?

 
 
 

NO.26 A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.
How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

 
 
 

NO.27 An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple reports with the option to select a specific portfolio, sorted in a descending order, so the most expensive projects appear on top. Which steps should be taken to create this report?

 
 
 

NO.28 A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?

 
 
 

NO.29 How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

 
 
 

NO.30 A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

 
 
 

NO.31 What is unique to a Scrum iteration?

 
 
 

NO.32 A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

 
 
 

NO.33 What parent object can have child objects?

 
 
 

NO.34 Which date type should an assignee update to change the completion date of a task?

 
 
 
 

NO.35 A project manager is assigned to a new Workfront request. The request specifies that the management team’s sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?

 
 
 

NO.36 A user wants to add users to a proof based on who requested the project and the additional approvers listed in the request.
Which Workflow should the user choose?

 
 
 

NO.37 Which Workfront collection of users allows a task or issue to be assigned to multiple people?

 
 
 

NO.38 A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

 
 
 

NO.39 The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?

 
 
 

NO.40 Refer to the exhibit.

Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?

 
 
 

NO.41 A project manager is managing a project and realizes a task is delayed. They want to see how downstream tasks are impacted.
Which feature of the Gantt chart will help them understand this?

 
 
 

Adobe AD0-E911 Exam Syllabus Topics:

Topic Details
Topic 1
  • Intake and Planning: Covers how work requests are received, reviewed, and planned in Workfront, including task settings, permissions, project hierarchy, risk tracking, and relevant reporting during the planning phase.
Topic 2
  • Closeout: Covers the actions and evaluations required when closing a project, including object status triggers and measuring overall project success.
Topic 3
  • Execute: Covers the active management of projects in Workfront, including milestones, approvals, resource assignment, financial tracking, team communication, proofing, Gantt charts, and custom reporting during project execution.

 

Authentic AD0-E911 Dumps With 100% Passing Rate Practice Tests Dumps: https://www.latestcram.com/AD0-E911-exam-cram-questions.html

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

leave a comment

Enter the text from the image below