120 Exam Questions for AACE-PSP Updated Versions With Test Engine
Pass AACE-PSP Exam with Updated AACE-PSP Exam Dumps PDF 2023
NO.71 There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
NO.72 Total float is defined as the amount of time an activity can be delayed without impacting
NO.73 How much Total Float does drafting the product manual have?
NO.74 Which of the following is NOT required when performing weekly or monthly schedule updates?
NO.75 Which of the following is NOT a tool or technique used to perform scope planning?
NO.76 Which of the following will always describe the critical path? The path with
NO.77 What is the result of a forward pass calculation?
NO.78 If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
NO.79 During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
NO.80 Each of the following accurately describes total float in a schedule EXCEPT:
NO.81 At a minimum, periodic reporting must be done at what interval?
NO.82 You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company’s board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule’s work activity durations?
NO.83 The linear scheduling velocity diagram has the following two-axis:
NO.84 The work breakdown structure is used to organize
NO.85 Which of the following phases does NOT describe the commonly accepted construction life cycle?
NO.86 Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
NO.87 An early start constraint dictates
NO.88 Determine the correct formula and date for the late finish for Activity 2002.
NO.89 Estimate to complete (ETC) is __________________.
NO.90 Using the “crashed” schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
NO.91 In a “crashed” schedule, which is a chain of activities that precede activity 2004?
AACE-PSP Exam Dumps – Free Demo & 365 Day Updates: https://www.latestcram.com/AACE-PSP-exam-cram-questions.html
Save my name, email, and website in this browser for the next time I comment.
120 Exam Questions for AACE-PSP Updated Versions With Test Engine [Q71-Q91]
120 Exam Questions for AACE-PSP Updated Versions With Test Engine
Pass AACE-PSP Exam with Updated AACE-PSP Exam Dumps PDF 2023
AACE-PSP Exam Dumps – Free Demo & 365 Day Updates: https://www.latestcram.com/AACE-PSP-exam-cram-questions.html
Related Certifications
Recent Posts
Archives
Categories